Planning for cycling and walking

Basic Information

Mobility solution ID

P1.2

Timeline

- complete

Project

DYN@MO

Summary

Stakeholders and citizens have identified the need for improvements of the cycling and walking networks of Palma as a priority. The establishment of healthy and safe walking routes and the expansion of the bicycle network constitute a core planning element defined in the SUMP. The measure aimed to increase the modal share of walking and cycling and further enhance the attractiveness of the historic city centre. In addition, the city would expand the public bike system with 150 new bicycles.

Implementing sustainable mobility

Within this measure and with involvement of the local stakeholders, Palma planned to significantly extend the current cycling network and walking routes in the city. It has been integrating cycling and walking policies into the general framework of the Sustainable Urban Mobility Plan. The city has been also establishing a network of health-oriented routes to promote safe walking for older and/or disabled citizens in different areas of the city. By developing the missing links in the network of cycling lanes, bicycles could become a viable alternative to private cars for trips within the city.

The main objectives of this measure were to:

  • Implement initial steps related to planning, as defined in the SUMP, involving local stakeholders and citizens
  • Plan and realise the expansion of the public bike system
  • Plan and establish two healthy walking routes for old and disabled people
  • Plan and realise missing links in the network of cycling lanes, covering at least 5 km
  • Promote cycling and walking as a mode of transport
  • Increase the number of cycling trips in the CIVITAS area by 20%
  • Increase the modal share of walking trips in the CIVITAS area
  • Increase the quality of public space by reducing road space for private cars

Progress

A mobility survey conducted in 2009 indicated that cycling and walking together account for 38% of the trips within the city of Palma. The share of cycling was still too low to be measured separately. Since 2007, 17.5 kilometres of cycling lanes have been established, bringing the total length of cycling lanes to 43.5 kilometres at the beginning of 2011. A new public bicycle service was implemented in the city in April 2011 with 300 bicycles.

Car access has been restricted in the historic city centre since the 1990s. In 2009, the original barriers were replaced by a video camera system equipped with licence plate recognition software. Walking is the main means of transport in the historic city centre. In 2011, the Palma conducted an inventory of physical barriers in public spaces and public buildings for older people and disabled citizens in order to advance the city's accessibility plan. It also created pedestrian areas in the historic city centre as well as beside two routes towards the city centre.

 

Planning & preparation

During the preparation phase of the CIVITAS measure the following tasks were carried out within the framework of the SUMP development:

  • Study on location of new stands for public bikes and market study on expansion of number of bicycles
  • Citizen (residents and businesses, public medical sector, old people associations, disabled people associations) participation events and tools for the first two healthy walking routes and the new cycling connections, including:
  • a kick-off event in the area of each of the two healthy walking routes to discuss ideas with stakeholders
  • Up to 5 information events to show the basic design options of healthy walking routes and cycling lanes
  • Design and planning of new cycling routes
  • Design and planning of two healthy walking routes (safe routes)

 

Implementation & demonstration

In the implementation phase the following tasks were executed:

  • Two healthy walking routes in the areas of the health centres, Son Gotleu and Valldargent, have been inaugurated. The city has manipulated public spaces and traffic lights to make the routes more accessible for people with reduced mobility.
  • Seven safe routes to school have been established with small changes in infrastructure to increase safety for walking and cycling.
  • 150 new bicycles and 175 new anchor points have been added to the public bike system, BiciPalma. Nine new BiciPalma stations were introduced to cover more neighborhoods. The system was opened to visitors and tourists.
  • Second extension is taking place  with 100 additional bikes, 100 anchor points and 5 new stations
  • Over 16 kilometres of new cycling lanes were developed during the project, already tripling the original objective.

Outcomes

Tangible outputs:

  • 2 idea-generating events for healthy walking routes with stakeholders
  • 5 information events on the new infrastructures for slow modes
  • Expansion of public bike system with 150 new bicycles and  175 new anchor points
  • 16 kilometres of cycling lanes
  • Two healthy and safe accessible walking routes
  • Development of 7 safety paths to school
  • 2 Promotion campaigns (one on walking and one cycling)
  • Private car restriction in the historic center and 30 km/h limit in all the area.

Expected outcomes in the short- to medium-term:

  • Increased number of cyclists in the CIVITAS area by 20%
  • Increased share of walking trips by 20%
  • Increase in the number of uses of the public bike system

Expected outcomes in the mid- to long-term:

  • Reduced congestion
  • Reduced emissions in the city centre
  • Increase in cycling trips for personal and business purposes

 

Latest

.eu web awards
covenantofmayors.eu
ELTIS / Urban Mobility Observatory LOGO
European Mobility Week
INTERREG LOGO
netzerocities logo
Smart Cities Marketplace
EU Logo

Funded by the European Union. Views and opinions expressed are however those of the author(s) only and do not necessarily reflect those of CINEA. Neither the European Union nor CINEA can be held responsible for them.

This website is hosted by an environmentally-friendly server provider.